Overhead System Improvements as of January 2012

General Project Area Project Type Project Status
Pt Fosdick Dr NW & 10th St NW Overhead System Improvement In Design
94th Ave NW Overhead System Improvement In Design
Delano Rd / Ulsh Rd  Overhead System Improvement In Design
Minter Sub to Vaughn Sub Backup Overhead System Improvement In Design
Murphy Dr - 38th Ave to Olsen Dr Overhead System Improvement In Design
     
Sidney Rd SW Overhead System Improvement In Construction
Sehmel Dr NW & 74th Ave NW Overhead System Improvement In Construction
Wright Bliss Rd KPN Overhead System Improvement In Construction
Erickson Rd KPN/ Key Pen Hwy So Overhead System Improvement In Construction
50th St KPN / Key Pen Hwy N Overhead System Improvement In Construction
160th St KPN Overhead System Improvement In Construction
Delano Rd KPS Overhead System Improvement In Construction
Delano Rd / Woodworth Dr KPS Overhead System Improvement In Construction
     
66th Ave / 158th Ave  Overhead System Improvement Completed
86th Ave - David Day Dr to 92nd St Overhead System Improvement Completed
9th Ave KPHN Overhead System Improvement Completed

 

Underground Conversion Projects as of January 2012

General Project Area Project Type Project Status
215th Ave KPS OH to UG Conversion In Design
Wollochet Dr 40th St NW to 30th St NW OH to UG Conversion In Design
Wollochet Dr East Bay to Fillmore  OH to UG Conversion In Design
South Herron Line OH to UG Conversion In Design
149th St NW West of 88th Ave NW OH to UG Conversion In Design
88th Ave NW between 145th /150th OH to UG Conversion In Design
143rd St Ct NW West of 82nd Ave NW OH to UG Conversion In Design
144th St NW West of 82nd Ave  OH to UG Conversion In Design
145th St NW between 82nd / 88th  OH to UG Conversion In Design
149th St NW East of 82nd Ave NW OH to UG Conversion In Design
Goldman Dr NW  OH to UG Conversion In Design
7th Lane and Chinook Dr, FI OH to UG Conversion In Design
Crescent Valley Dr  OH to UG Conversion In Design
Aqua Drive & Lakeview Way OH to UG Conversion In Design
Thomas Rd Phase 2 OH to UG Conversion In Design
Thomas Rd Phase 1 OH to UG Conversion In Design
24th Ave off Stone Dr OH to UG Conversion In Design
12th Ave FI OH to UG Conversion In Design
     
97th Ave Ct NW OH to UG Conversion In Construction
32nd St from 70th Ave to 62nd Ave  OH to UG Conversion In Construction
Bella Bella OH to UG Conversion In Construction
Fox Dr & 9th Ave OH to UG Conversion In Construction
150th St between 82nd / 88th  OH to UG Conversion In Construction
70th St Ct KPN OH to UG Conversion In Construction
Island Blvd FI OH to UG Conversion In Construction
Gway, 10th & Hyak FI OH to UG Conversion In Construction
82nd Ave South OH to UG Conversion In Construction
Reid Dr & 14th Ave OH to UG Conversion In Construction
Hunt St west of 46th Ave OH to UG Conversion In Construction
     
Wollochet Dr, 40th St to Fillmore Dr OH to UG Conversion Completed
Stone Dr OH to UG Conversion Completed
Fox Dr OH to UG Conversion Completed
Hilltop Dr NW OH to UG Conversion Completed
     
General Project Area Project Type Project Status
SR16 & 144th St  UG Cable Replacement In Design
83rd St Ct NW UG Cable Replacement In Construction
158th Ave KPS UG Cable Replacement In Construction
122nd St KPN UG Cable Replacement In Design
Peninsula High School UG Cable Replacement In Design
Mahnke Rd KPS UG Cable Replacement In Construction
8th St NW / 42nd Ave NW UG Cable Replacement In Construction
Key Pen Hwy/ 121st St NW UG Cable Replacement In Design
     
General Project Area Project Type Project Status
Jackson Lake Rd - 186th Av  UG System Improvement In Design
Stone Dr, 24th Ave to Point Fosdick Dr UG System Improvement In Design
SR 302 Danforth to Springbrook UG System Improvement Completed